El Centro Aquatic Center
2 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2016121045
- Lead Agency
- City of El Centro
- Document Title
- El Centro Aquatic Center
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 6/26/2017
- Present Land Use
- Existing LU is a city park and roadway; Limited use zone/public; and GP: Public
- Document Description
- The project consist of the construction of a 3.5 acre aquatic center at Adams Park from 4th St to 6th St in El Centro, CA. Proposed facilities at the site include four swimming pools, aquatic center building, parking lot, and a pool equipment building. Swimming pools at the site will include an eight lane competition pool, instructional/warm-up pool, recreational pool, and a lazy river. The aquatic center building will contain staff offices, locker rooms, restrooms, concession stand and an event area. Access to the site will be via two entrances from Park Avenue. 5th St from Park Ave to Adams Ave would have to be vacated as a result of the project.
- Contact Information
-
Norma Villicana
City of El Centro
Lead/Public Agency
1275 Main Street
El Centro, CA 92243
Phone : (760) 337-4545
Location
- Coordinates
- 32°47'44.5"N 115°33'19.5"W
- Cities
- El Centro
- Counties
- Imperial
- Cross Streets
- Adams Ave and 6th St
- Zip
- 92243
- Total Acres
- 3.5
- Parcel #
- 053-041-001, -044-001
- State Highways
- 8, 86
- Railways
- UPRR
- Schools
- McKinley ES
Notice of Determination
- Approving Agency
- City of El Centro
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- 1275 W. Main St., El CEntro, CA 92243
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.