La Cadena Drive Over the Santa Ana River Bridge Replacement
2 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2016121036
- Lead Agency
- Colton, City of (City of Colton)
- Document Title
- La Cadena Drive Over the Santa Ana River Bridge Replacement
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 3/2/2017
- Present Land Use
- Transportation/major arterial roadway (La Cadena Dr)
- Document Description
- The proposed project would replace the existing La Cadena Drive bridge with a new 98-foot wide bridge that would accommodate four 12 ft lanes (two lanes in each direction), a 14-ft wide striped median, a 5 ft class II bike lane within the 9ft, 6-in shoulder, and a 6 ft sidewalk protected by a 1 ft, 6-in wide concrete barrier in each direction. The proposed project would also replace the existing access to the Santa Ana River Trail parking lot and a portion of the existing bike trail connection between the SART and southbound side of La Cadena Drive.
- Contact Information
-
Victor Ortiz
City of Colton
160 S. 10th St
Colton, CA 92324
Phone : (909) 370-6131
Location
- Coordinates
- 34°045'2.45"N 117°3.31'3.36"W
- Cities
- Colton
- Counties
- San Bernardino
- Cross Streets
- La Cadena Dr/W Tropica Rancho Rd
- Zip
- 92324
- Total Acres
- 32.03
- Parcel #
- near 0163-402-01
- State Highways
- I-10, 215
- Railways
- BNSF, UPRR
- Schools
- Multiple Schools
- Waterways
- Santa Ana River
- Base
- Jurupa
Notice of Determination
- Approving Agency
- City of Colton
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- 160 S. 10th Street, Colton, CA 92324
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.