South Palm Canyon Drive Bridge Replacement (Lake or Streambed Alteration Agreement No. 1600-2017-0004-R6)

3 Documents in Project

Summary

SCH Number
2016121010
Lead Agency
City of Palm Springs
Document Title
South Palm Canyon Drive Bridge Replacement (Lake or Streambed Alteration Agreement No. 1600-2017-0004-R6)
Document Type
NOD - Notice of Determination
Received
Posted
10/9/2017
Present Land Use
Roadway/Bridge
Document Description
CDFW has executed Lake and Streambed Alteration Agreement No. 1600-2017-0004-R6, pursuant to section 1602 of the Fish and Game Code to the project Applicant, the City of Palm Springs. Project is limited to the replacement of the existing structurally deficient bridge (Bridge # 56C0408) with a new bridge that will be sufficiently wide to support a median, two standard 12-foot wide lanes in each direction, a shoulder that can accommodate a Class II bike lane and an ADA compliant sidewalk on both sides. Proposed roadway improvements include providing horizontal transitions from the proposed new bridge section and the existing South Palm Canyon Dr. proposed CV-link trail along Tahquitz Creek Channel.

Contact Information

Name
Charles Land
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Cities
Palm Springs
Counties
Riverside
Cross Streets
South Palm Canyon Dr south of the intersection of East Sunny Dunes Rd
Zip
92262
Total Acres
3
Parcel #
multiple
State Highways
111
Airports
Palm Springs
Waterways
Tahquitz Creek Channel, Whitewater River

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No