South Palm Canyon Drive Bridge Replacmeent over the Tahquitz Crek Channel. City Project No. 12-02
3 Documents in Project
Summary
SCH Number
2016121010
Lead Agency
City of Palm Springs
Document Title
South Palm Canyon Drive Bridge Replacmeent over the Tahquitz Crek Channel. City Project No. 12-02
Document Type
NOD - Notice of Determination
Received
Posted
4/10/2017
Present Land Use
Roadway/Bridge
Document Description
The proposed project will result in the replacement of the existing structurally deficient bridge (State Bridge No. 56C0408) on South Palm Canyon Dr. at the Tahquitz Creek Channel. The existing bridge has been rated by Caltrans to be structurally deficient primarily because it cannot accommodate current standard vehicular design loads or permit loads. The purpose of the project is to replace the existing structurally deficient bridge with a new wider bridge at the same location to ensure public safety, enhance vehicular and non-motorized traffic circulation in the area, and remove the bridge from the federal Eligible Bridge List. The need for the project is to construct a new bridge that meets current design standards and accommodate the local requirements.
Contact Information
Name
Edward Robertson
Agency Name
City of Palm Springs
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Palm Springs
Counties
Riverside
Cross Streets
South Palm Canyon Dr south of the intersection of East Sunny Dunes Rd
Zip
92262
Total Acres
3
Parcel #
multiple
State Highways
111
Airports
Palm Springs
Waterways
Tahquitz Creek Channel, Whitewater River
Notice of Determination
Approving Agency
City of Palm Springs
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes