Anderson Stream Crossing and Pond Project (Lake or Streambed Alteration Agreement No. EPIMSMEN-13374-R1)
384 Documents in Project
Summary
SCH Number
2016112028
Lead Agency
Mendocino County
Document Title
Anderson Stream Crossing and Pond Project (Lake or Streambed Alteration Agreement No. EPIMSMEN-13374-R1)
Document Type
NOD - Notice of Determination
Received
Posted
4/22/2021
Document Description
The project is limited to four (4) encroachments. Three (3) encroachments are to upgrade undersized and/or failing culverts. Work for these encroachments will include excavation, removal of the existing culverts, replacement with new appropriately-sized culverts, backfilling and compaction of fill, and rock armoring as necessary to minimize erosion. One (1) encroachment is to install a rock apron downstream from the outlet culvert of an existing pond, and remove diversion infrastructure. Water will not be diverted from the pond for consumptive use.
Contact Information
Name
Angela Liebenberg
Agency Name
CDFW
Contact Types
Responsible Agency
Address
Phone
Location
Cities
Covelo
Counties
Mendocino
Regions
Northern California
Other Location Info
The project to be completed is located within the Eel River watershed, approximately 4 miles northwest of the town of Covelo, County of Mendocino, State of California. The project is located in Section 27, T23N, R13W, Mt. Diablo Base and Meridian; in the Covelo West U S. Geological Survey 7.5- minute quadrangle.
Notice of Determination
Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
County Clerk
Mendocino
Final Environmental Document Available at
County of Mendocino
860 N. Bush Street
Ukiah, CA 95482
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Attachments
Notice of Determination
Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.