Butte & Ash Creek Bridge Replacement Project

5 Documents in Project

Summary

SCH Number
2016112013
Lead Agency
California Department of Transportation, District 2
Document Title
Butte & Ash Creek Bridge Replacement Project
Document Type
NOD - Notice of Determination
Received
Posted
3/27/2017
Present Land Use
Caltrans ROW
Document Description
Caltrans proposes to replace two bridges along SR 299 in Modoc County. The purpose of the project is to restore the long-term reliability of the Butte Creek Bridge and Ash Creek Bridge, and reduce the need for continued maintenance and repairs. Work activities would include the construction of two new bridges on their existing alignment, installation of new guardrails and bridge railing, reconstruction of approach pavement and shoulders to conform to the new bridges, and the improvement of road connections within the project limits. The project would require vegetation clearing, temporary construction easements, and acquisitions of new ROW. The project would include water diversion at Ash Creek Bridge, and pile driving at both the Butte Creek and Ash Creek Bridges.

Contact Information

Name
Chris Quiney
Agency Name
California Department of Transportation, District 2
Contact Types
Lead/Public Agency

Location

Counties
Modoc
Cross Streets
SR 299
Zip
96006
Total Acres
3.5
Parcel #
Caltrans ROW
State Highways
299
Airports
Adin
Schools
Big Valley Primary
Waterways
Butte Creek and Ash Creek
Township
39N
Range
9E
Section
21,28
Other Location Info
Adin

Notice of Determination

Approving Agency
Caltrans
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.