Bonelli Equestrian Center Refurbishment Project
2 Documents in Project
Summary
SCH Number
2016111046
Lead Agency
Los Angeles County
Document Title
Bonelli Equestrian Center Refurbishment Project
Document Type
NOD - Notice of Determination
Received
Posted
8/11/2017
Present Land Use
GP: Open space, RP-Regional Park; Z: Open space
Document Description
The county proposes to refurbish Bonelli Equestrian Center in Frank G. Bonelli Regional Park, including removal of existing horse stables and other structures, and construction/installation of a barn with 24 stalls, a concession building with restrooms, fencing, a retaining wall, security lighting, a horse pan, picnic tables, and improvements to infrastructure (i.e. water, sewer, and storm water drainage). An existing drainage ditch in the northern portion of the project site would be regraded, and the project would include an approximately 3,000 sf biofiltration planter (i.e. detention basin) immediately east of the equestrian center for collection of on site storm water runoff.
Contact Information
Name
Julie Yom
Agency Name
Los Angeles County
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
San Dimas
Counties
Los Angeles
Cross Streets
Bonelli Equestrian Center in Frank G. Bonelli Regional Park (120 Via Verde, San Dimas)
Zip
91773
Total Acres
5.5
Parcel #
8378-022-913
State Highways
SR 57, SR 71
Railways
Santa Fe
Airports
Brackett Field Airport
Schools
3 high, 1 MS
Waterways
Puddingstone Reservoir
Township
1S
Range
9W
Base
SBBM
Notice of Determination
Approving Agency
County of LA
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.