Anaheim Resort Electric Line Extensions Project
2 Documents in Project
Summary
SCH Number
2016111032
Lead Agency
City of Anaheim
Document Title
Anaheim Resort Electric Line Extensions Project
Document Type
NOD - Notice of Determination
Received
Posted
2/10/2017
Present Land Use
Transitional; GP=Public institutional; LU:J Utility, public
Document Description
Project is the extension of an underground electric line that will connect to existing substation circuit breakers. Approximately 8,000 lf of cable line will be pulled through an existing ductbank, and approximately 11,000 lf will be installed within a new ductbank. The new ductbanks will require a trench generally excavated to a depth of 4-10 ft at a width of approximately 2 ft. Additionally approximately 2,500-3,000 lf of ductbank will be installed on Cerritos Ave and Anaheim Blvd for the future installation of a 69kV line that will be installed under a future project in mid-2017. The areas of ductbank total approximately 4.25 miles. Other project features include install of risers and vaults max vault depth = 10ft x 8ft x 20ft long.
Contact Information
Name
Fred Barvarz
Agency Name
City of Anaheim
Contact Types
Lead/Public Agency
Phone
Location
Cities
Anaheim
Counties
Orange
Cross Streets
Cerritos Ave, Walnut St, Magic Way, Ninth St, Disney Wy, Disneyland Dr, Lewis St
Zip
92802
Total Acres
4 mi
Parcel #
varies
State Highways
5
Railways
LOSSAN
Schools
Ball Jr. HS, Stoddard E
Waterways
Santa Ana River
Notice of Determination
Approving Agency
City Council
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.