Bay Bridge pump Station and Force Mains Replacement Project

7 Documents in Project

Summary

SCH Number
2016111031
Lead Agency
Orange County Sanitation District
Document Title
Bay Bridge pump Station and Force Mains Replacement Project
Document Type
NOD - Notice of Determination
Received
Posted
7/27/2023
Document Description
In response to the limited writ of mandate, OC San has prepared an Addendum to the EIR that: (1) provides additional information regarding the use of Lower Castaways Park as a construction staging area; (2) identifies an additional construction staging area at OC San Plant No. 2 for soil storage/drying activities; (3) modifies mitigation measure TRA-1 to eliminate any reference to additional construction staging or material storage areas; and (4) modifies and addresses the enforceability of Mitigation Measure AES-1. Collectively, these clarifications and additions are referred to as the “Modified Project.”

Contact Information

Name
Kevin Hadden
Agency Name
Orange County Sanitation District
Job Title
Principal Staff Analyst
Contact Types
Lead/Public Agency / Project Applicant

Location

Cities
Newport Beach
Counties
Orange
Regions
Southern California
Cross Streets
East Coast Highway and Bayside Drive
Zip
92660
Total Acres
31.4
Parcel #
440-132-60, 117-801-10
State Highways
SR-1
Railways
N/A
Airports
N/A
Schools
Numerous
Waterways
Newport Bay Channel
Township
6S
Range
10W
Section
26
Base
SBBM

Notice of Determination

Approving Agency
Orange County Sanitation District
Approving Agency Role
Lead Agency
Approved On
County Clerk
Orange
Final Environmental Document Available at
https://www.ocsan.gov/about-us/transparency/eir-documents/-folder-807

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
Yes (Addendum)
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.