110 Dry Creek Road Mixed Use Project (Streambed Alteration Agreement No. 1600-2017-0011-R3)

3 Documents in Project

Summary

SCH Number
2016102013
Lead Agency
Healdsburg, City of (City of Healdsburg)
Document Title
110 Dry Creek Road Mixed Use Project (Streambed Alteration Agreement No. 1600-2017-0011-R3)
Document Type
NOD - Notice of Determination
Received

Document Description
CDFW has executed Lake and Streambed Alteration Agreement No. 1600-2017-0011-R3, pursuant to section 1602 of the Fish and Game Code to the project Applicant, City of Healdsburg. The Permittee proposes to demolish five structures on the Project site and develop a four-story, 84,075 sq. ft. hotel, and 42 affordable multi-family units, with parking on the 3.97-acre site. Additionally, a single combined vehicular and pedestrian bridge that is approved by the City of Healdsburg (Exhibit B) will be constructed. Construction of the bridge will cause approx. .006 acres of direct impacts and .027 acres of indirect impacts to the riparian woodland associated with the project. The approx. 40-foot long vehicle bridge includes abutments, wingwalls, and armored protection for the bridge. Stormwater will be rerouted to connect to the existing Grove Street storm water system.

Contact Information
Karen Weiss
CDFW
7329 Silverado Trail
Napa, CA 94558

707-944-5525

Location

Coordinates
38°6.2'52"N 122°8.7'4.9"W
Cities
Healdsburg
Counties
Sonoma
Cross Streets
Dry Creek Rd and Grove St
Zip
95448
Total Acres
3.87
Parcel #
089-082-030-000
Railways
Northwestern Pacific
Airports
Healdsburg
Schools
Healdsburg USD
Waterways
Foss Creek
Township
10
Range
9W
Section
36
Base
MD

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
7329 Silverado Trail, Napa, CA 94558

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
No
Download CSV New Search