Southern California Edison Transmission Tower Replacement Project Harbor Development Permit No. 16-025
5 Documents in Project
Download CSV
Download All Attachments
New Search
Print
Summary
- SCH Number
- 2016101061
- Lead Agency
- Long Beach, Port of (Port of Long Beach)
- Document Title
- Southern California Edison Transmission Tower Replacement Project Harbor Development Permit No. 16-025
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 6/4/2020
- Project Applicant
- Southern California Edison Company
- Document Description
- An addendum to the Southern California Edison Transmission Tower Replacement Project (Project) Final EIR certified by the Long Beach Board of Harbor Commissioners in December 2017 has been prepared to evaluate minor technical modifications to the approved project proposed by Southern California Edison Company, comprised of: (1) Addition of ground improvements to the driven pile foundation design for the new towers M0-T2X (Pier S) and M0-T3X (Pier B) to combat the effect of lateral spreading and allow driven piles to be viable at all locations. (2) A modification to Mitigation Measure BIO-4 to allow no more than 5 percent permanent loss of Southern Tarplant associated with construction activities, such as crushing by construction equipment, vehicles, or foot traffic. This 5 percent permanent loss is in addition to the no more than 10 percent temporary impacts of the on-site population on the south side of the Cerritos Channel.
- Contact Information
-
Alex Holford
Port of Long Beach
City of Long Beach Harbor Department 415 West Ocean Boulevard
Long Beach, CA 90802
Phone : (562) 283-7100
Location
- Cities
- Long Beach
- Counties
- Los Angeles
- Other Location Info
- Port of Long Beach Cerritos Channel Crossing, near Carrack Avenue and Pier A Way in the City of Long Beach, California; County of Los Angeles
Notice of Determination
- Approving Agency
- City of Long Beach
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- This is to certify that the electronic record of the Long Beach Board of Harbor Commissioners' approval for the Project is available for review to the general public at: https://www.polb.com/ceqa.
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- No
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- Yes
- (5) A Statement of Overriding Considerations was adopted for this project
- Yes
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Attachments
- Notice of Determination
- 20200527 NOD_FINAL Addendum SCE FEIR Transmission Tower Replacement Project PDF 2008 K EIR Addendum PDF 777 K
Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.