Tesoro del Valle (Phases A, B, and C) Project - Water Supply Permit Amendment

6 Documents in Project

Summary

SCH Number
2016101032
Lead Agency
Los Angeles County
Document Title
Tesoro del Valle (Phases A, B, and C) Project - Water Supply Permit Amendment
Document Type
NOD - Notice of Determination
Received
Posted
12/8/2023
Document Description
The Applicant proposes operate two 1.2-million-gallon welded steel tanks (Tesoro Tank 3 and Tesoro Tank 3A), a new pump station, a new booster station (Booster 3), and pressure zone 3. The new water system components were built by the developer to serve the new Tessoro del Valle development Project which includes construction of 820 residential units,19.1 acres of parks and other recreational amenities, a 2.1-acre helispot, an internal circulation system, and associated infrastructure including utilities. Project development would occur on a footprint of approximately 393.6 acres. Once the water system components are built, they are given to the water system to operate.

Contact Information

Name
Chi Diep
Agency Name
State Water Resources Control Board, Division of Drinking Water
Job Title
District Engineer
Contact Types
Responsible Agency

Location

Cities
Santa Clarita
Counties
Los Angeles
Regions
Citywide
Cross Streets
San Francisquito Canyon Road

Notice of Determination

Approving Agency
State Water Resources Control Board
Approving Agency Role
Responsible Agency
Approved On
County Clerk
Los Angeles
Final Environmental Document Available at
https://ceqanet.opr.ca.gov/Project/2016101032

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print