City of Weed Bypass Water Supply Pipeline Project

7 Documents in Project

Summary

SCH Number
2016092058
Lead Agency
City of Weed
Document Title
City of Weed Bypass Water Supply Pipeline Project
Document Type
NOD - Notice of Determination
Received
Posted
4/27/2018
Present Land Use
GP & Z: Various; Use: public utilities located within public road ROW and public utility easements
Document Description
The City of Weed adopted a MND for the Bypass Water Supply Pipeline Project On Dec. 8, 2016. Following adoption of the MND, the City determined that revisions to the project were required to ensure a safe and reliable water supply, and an Addendum (Addendum NO. 1) to the previously adopted MND was prepared. Following adoption of Addendum No. 1, geotechnical testing revealed that geological constraints would not allow trenchless installation of the pipe up School Hill as originally proposed, and the original alignment was too steep to allow safe installation with open-cut trenching. It was determined the pipe could be safely installed using open-cut trenching further north on School Hill. The modified alignment includes additional pipeline improvements in the road rights-of-way of Olive Street and/or E. Lake Street, Clay Street, E. Inez Street, and Butte Street. The subject properties are not included on any list of hazardous waste facilities/sites pursuant to Section 65962.5 of the CA Government Code.

Contact Information

Name
Ron Stock
Agency Name
City of Weed
Contact Types
Lead/Public Agency

Location

Cities
Weed
Counties
Siskiyou
Cross Streets
Various
Zip
96094
Parcel #
various
State Highways
5,97, 265
Railways
UP
Schools
Weed ES, Weed HS
Waterways
Boles Creek, Beaughton Creek, Black Butte Spring, etc.
Township
41N
Range
5W
Section
1,11,1
Base
MDMB

Notice of Determination

Approving Agency
City of Weed City Council
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print