Cal Water MPS Station 6 Potable Water Tank Reconstruction Project

3 Documents in Project

Summary

SCH Number
2016092025
Lead Agency
City of Hillsborough
Document Title
Cal Water MPS Station 6 Potable Water Tank Reconstruction Project
Document Type
NOD - Notice of Determination
Received
Posted
7/18/2017
Present Land Use
Public facilities and services
Document Description
The new concrete tank would be a different shape than the existing tank. The shape of the new tank allows Cal Water to increase storage capacity at the MPS Station 6 site by approximately nine percent (3.05 vs. 2.8 million gallons) while at the same time reducing the surface area occupied by the tank by approximately 20% (24,806 sf vs. 30,976 sf). The new tank would increase storage capacity within the Cal Water's Bayshore District and improve the efficiency and reliability of the District's water distribution system, especially during a seismic related event. Cal Water would not modify the exterior of the existing pump station, other than the addition of new, exterior lighting.

Contact Information

Name
Neal Martin
Agency Name
City of Hillsborough
Contact Types
Lead/Public Agency

Location

Cities
Hillsborough
Counties
San Mateo
Cross Streets
Crystal Springs Rd, Alameda de las Pulgas, Irving St, Cornell Ave
Zip
94010
Total Acres
1.9
Parcel #
032-395-220
State Highways
82, 92, 280
Railways
CalTrain
Schools
various
Waterways
Lower Crystal Springs Reservoir, several small creeks
Township
4S
Range
4W

Notice of Determination

Approving Agency
Town of Hillsborough
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print