Mammoth Creek Gap Closure Project

3 Documents in Project

Summary

SCH Number
2016092007
Lead Agency
Mammoth Lakes, City of (City of Mammoth Lakes)
Document Title
Mammoth Creek Gap Closure Project
Document Type
NOD - Notice of Determination
Received
Posted
11/28/2016
Present Land Use
Residential, high density residential 2, open space

Document Description
The proposed project involves the construction of a Class 1 multi use path that will be designed to connect from Minaret Rd to an existing MUP on the west side of Minaret Rd. The MUP will run east-west, paralleling Old Mammoth Rd on the south side of Mammoth Creek and to the north of Old Mammoth Rd. The MUP will be ten ft wide and compliant with Caltrans and Americans with Disabilities Act Requirements. The path will be paved with asphalt of sufficient strength to support snow removal. Additional improvements include the installation of a pedestrian activated signal across Minaret Road, installation of safety lighting adjacent to the path, and the replacement of an existing pedestrian bridge crossing Mammoth Creek, using the existing abutments and requiring no excavation.

Contact Information
Jamie Robertson
City of Mammoth Lakes
P.O. Box 1609 437 Old Mammoth Road, Suite R
Mammoth Lakes, CA 93546

Phone : (760) 965-3653

Location

Coordinates
37°37'"N 118°58'16.6"W
Cities
Mammoth Lakes
Counties
Mono
Cross Streets
Minaret Rd and Old Mammoth Rd
Zip
93546
Total Acres
0.30
Parcel #
040-020-001-000, -000-000
State Highways
SR 203
Schools
Mammoth Unified
Waterways
Mammoth Creek
Township
4S
Range
27E
Section
S2
Base
BLM

Notice of Determination

Approving Agency
Town of Mammoth Lakes
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
437 Old Mammoth Road, Suite #, Mammoth Lakes, CA 93546

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes
Download CSV New Search