Addendum to Mitigated Negative Declaration for Sleepy Hollow Steelhead Rearing Facility Upgrade

4 Documents in Project

Summary

SCH Number
2016091071
Lead Agency
Monterey Peninsula Water Management District
Document Title
Addendum to Mitigated Negative Declaration for Sleepy Hollow Steelhead Rearing Facility Upgrade
Document Type
NOD - Notice of Determination
Received
Posted
7/20/2018
Present Land Use
Steelhead Rearing Facility/permanent grazing or farmland/greater monterey peninsula study area
Document Description
District proposes to upgrade the Sleepy Hollow Steelhead Rearing facility to improve water supply intake reliability and intake water quality. The project includes integrating or modifying existing systems to rear juvenile steelhead to work with proposed improvements. Specific tasks include: removing an existing water intake structure in the bed of the Carmel River; installing a new intake structure and screen in the bed of the Carmel River; piping and other improvements to deliver water from the river to the facility; and constructing a recirculating aquaculture system in the floodplain adjacent to the active channel of the Carmel River to provide water clarification and filtration. Project construction is anticipated to be phased, likely beginning in early 2017 and to be completed in 2019.

Contact Information

Name
Larry Hampson
Agency Name
Monterey Peninsula Water Mgt. Dist.
Contact Types
Lead/Public Agency

Location

Counties
Monterey
Cross Streets
~1 mile downstream of the former San Clemente Dam location
Zip
93924
Total Acres
3.2
Parcel #
417051004000
Waterways
Carmel River
Township
17S
Range
2E
Section
23
Base
MD
Other Location Info
Carmel Valley

Notice of Determination

Approving Agency
Monterey Peninsula Water Management District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
N/A
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print