Alipine County Administration Site - Interoperable Communication Tower

2 Documents in Project

Summary

SCH Number
2016062055
Lead Agency
Alpine County
Document Title
Alipine County Administration Site - Interoperable Communication Tower
Document Type
NOD - Notice of Determination
Received
Posted
9/6/2016
Present Land Use
County office building/institutional/institutional
Document Description
The proposed project is to fund and construct a communications tower. The purpose of the project is to improve public safety and interoperable communications among first responders in Alpine County. To accomplish the project purpose, the County of Alpine proposes to construct, maintain and operate a new 60 ft tall telecommunications monopole tower with ancillary antenna and associated equipment cabinet. The project will be located on the north side of the County Administrative Building at 99 Water Street on the north side of HWY 89 in the NE 1/4 of the SE 1/4 of Section 21, T10N, R20E.

Contact Information

Name
Brian Peters
Agency Name
Alpine County
Contact Types
Lead/Public Agency

Location

Counties
Alpine
Cross Streets
SR 89 & Water St
Zip
96120
Total Acres
0.94
Parcel #
002-280-005
State Highways
89
Waterways
Millberry Creek, Markleeville Creek
Township
10N
Range
20E
Section
21
Base
MDBM
Other Location Info
Markleeville

Notice of Determination

Approving Agency
Alpine County Board of Supervisors
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.