Addendum to the Facilities Master Plan Program EIR for the CCWRF Facility Asset Management and Improvement Project
14 Documents in Project
Summary
SCH Number
2016061064
Lead Agency
Inland Empire Utilities Agency
Document Title
Addendum to the Facilities Master Plan Program EIR for the CCWRF Facility Asset Management and Improvement Project
Document Type
NOD - Notice of Determination
Received
Posted
12/22/2021
Document Description
In March 2017, IEUA certified the Facilities Master Plan Program Environmental Impact Report (PEIR). The PEIR evaluated the potential environmental impacts associated with all of IEUA’s Master Plans. Among the identified projects for consideration was a capital improvement project, Project No. EN17006, at Carbon Canyon Water Recycling Facility (CCWRF). The 2015/2016 Asset Management Plan (AMP) provided the basic information used to the evaluate the CCWRF improvements in the PEIR. During design, additional asset improvements were deemed vital to address critical replacements of gates and the bridge crane system for the tertiary treatment. Since the tertiary treatment improvements were not included in the PEIR or the AMP, further evaluation of the PEIR was needed to confirm compliance with CEQA. Tom Dodson & Associates implemented a second-tier project evaluation and found the evaluation does not alter the conclusions contained in the PEIR document, no further analysis of the environmental impacts of the proposed modified project is required in a follow-on Negative Declaration or Supple-mental/Subsequent environmental impact report. The recommendation is to adopt an Addendum to the certified PEIR to include the findings from the second-tier project evaluation and certify the Addendum.
Contact Information
Name
Pietro Cambiaso
Agency Name
Inland Empire Utilities Agency
Job Title
Acting Manager of Strategic Planning and Resources
Contact Types
Lead/Public Agency
Phone
Email
Location
Cities
Chino
Counties
San Bernardino
Regions
Southern California
Cross Streets
north side of Chino Creek, south of Chino Hills Pkwy, east of Monte Vista Ave & west of Tel. Ave
Notice of Determination
Approving Agency
Inland Empire Utilities Agency
Approving Agency Role
Lead Agency
Approved On
County Clerk
San Bernardino
Final Environmental Document Available at
6075 Kimball Avenue, Chino, CA 91708
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
Yes (Addendum to PEIR)
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Attachments
Notice of Determination
Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.