Anaheim South Recycled Water Project (Project); Clean Water State Revolving Fund (CWSRF) No. C-06-8147-110

3 Documents in Project

Summary

SCH Number
2016061041
Lead Agency
Anaheim, City of (City of Anaheim)
Document Title
Anaheim South Recycled Water Project (Project); Clean Water State Revolving Fund (CWSRF) No. C-06-8147-110
Document Type
NOD - Notice of Determination
Received

Document Description
The project will install the recycled water supply and metering connection, a recycled water pump station with a tank, and distribution pipelines serving the southern area of Anaheim. Near Rampart Street, the project will construct a new turnout facility on the 66-inch diameter Groundwater Replenishment System pipeline. A new recycled water pump station will be located after immediately adjacent to the GWRS connection. An approx. 50,000 gallon recycled water fore bay/storage tank is planned to be constructed with the recycled water pump station to reduce peak flow effects to the GWRS. Total pipeline installation includes 42,300 linear feet; exclusive of Alternative A is an alternative to installation along Orangewood Avenue from I-5 Freeway to Harbor Blvd. Lateral connections will be made at various locations along the distribution system to connect customer meters.

Contact Information
Sahil Pathak
SWRCB
1001 I Street, 16th Floor
Sacramento, CA 95814

916-319-0220

Location

Coordinates
33°47'47.6"N 117°52'52.2"W
Cities
Anaheim
Counties
Orange
Cross Streets
Orangewood Ave., & Rampart; Anaheim Way & Stanford Ct
Zip
92806
Total Acres
8 mi
Parcel #
city streets; 232-011-19
State Highways
5 freeway
Railways
LOSSAN
Schools
Ponderosa ES
Waterways
Santa Ana River
Township
4S
Range
10W
Section
25

Notice of Determination

Approving Agency
State Water Board
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
1001 I Street, 16th Floor, Sacramento, CA 95814

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
N/A
Download CSV New Search