Bollinger Canyon Road Culvert Repair Project (Streambed Alteration Agreement No. 1600-2016-0278-R3)

4 Documents in Project

Summary

SCH Number
2016042021
Lead Agency
Moraga, City of (City of Moraga)
Document Title
Bollinger Canyon Road Culvert Repair Project (Streambed Alteration Agreement No. 1600-2016-0278-R3)
Document Type
NOD - Notice of Determination
Received

Document Description
CDFW has executed Lake and Streambed Alteration Agreement No. 1600-2016-0278-R3, pursuant to section 1602 of the Fish and Game Code to the Town of Moraga as represented by Mr. Edric Kwan. Project is limited to the fill of a 10 foot drop and undercut that has formed at a previously existing culvert along Bollinger Canyon Road. The existing outfall will have a retaining wall constructed above the top of bank and the undercut area and adjacent slope shall be armored with rock rip-rap and slope protection to stabilize the eroded area including filter fabric underneath the hardscape. Approx. 20 cubic yards of rock rip-rap and slope protection will be employed to fill the existing undercut and armor the adjacent slope to an area approx. 175 sq. ft.

Contact Information
Melissa Farinha
CDFW
7329 Silverado Trail
Napa, CA 94559

707-944-5579

Location

Coordinates
37°50'37.13"N 122°6'21.32"W
Cities
Moraga
Counties
Contra Costa
Cross Streets
Bollinger Canyon Rd and Joseph Dr
Zip
94556
Total Acres
<1
Parcel #
Town ROW
Schools
Yes
Waterways
Las Trampas Creek
Township
1S
Range
2W
Section
17

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
7329 Silverado Trail, Napa, CA 94559

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
No