Bollinger Canyon Road Culvert Repair Project

4 Documents in Project

Summary

SCH Number
2016042021
Lead Agency
City of Moraga
Document Title
Bollinger Canyon Road Culvert Repair Project
Document Type
NOD - Notice of Determination
Received
Posted
7/18/2016
Present Land Use
Residentia/Residential and Industrial /Community Facilities
Document Description
The Town of Moraga proposes to repair and reconstruct two culverts located in the Las Trampas Creek watershed along Bollinger Canyon Rd, between Joseph Dr and St. Mary's Rd. The purpose is to maintain existing storm drain conveyance and to stabilize an area adjacent to a storm drain outfall that has severely eroded. A section of Pipe 1 in poor condition would be replaced to maintain conveyance of storm water flows through the culvert. At Pipe 2, the outfall and adjacent slope will be armored with rock riprap and slope protection to stabilize the eroded area near the outfall. The stabilization solution for Pipe 2 requires fill of approximately 15 to 20 cy to stabilize the slope and culvert outfall. Not all of this fill would extend below the Ordinary High Water Mark (OHWM); the project footprint below the OHWM is approximately 175 sf. The project will also require the removal of approximately 8 trees.

Contact Information

Name
Edric Kwan
Agency Name
Town of Moraga
Contact Types
Lead/Public Agency

Location

Cities
Moraga
Counties
Contra Costa
Cross Streets
Bollinger Canyon Rd and Joseph Dr
Zip
94556
Total Acres
<1
Parcel #
Town ROW
Schools
Yes
Waterways
Las Trampas Creek
Township
1S
Range
2W
Section
17

Notice of Determination

Approving Agency
Town of Moraga
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print