Stevenson Bridge (23C0092) at Putah Creek Rehabilitation Project
2 Documents in Project
Summary
SCH Number
2016042001
Lead Agency
Solano County
Document Title
Stevenson Bridge (23C0092) at Putah Creek Rehabilitation Project
Document Type
NOD - Notice of Determination
Received
Posted
3/6/2025
Document Description
Bridge Rehabilitation - Seismic assessment of the bridge showed that many of the existing structural components of the bridge are unable to withstand seismic loads without retrofitting. Flexural and shear !demands exceeded the corresponding capacities, requiring retrofit or replacement of several structural members in order to meet safety requirements. Deficient components include the bridge railing, deck spalling and carbonation deck drains, cracking of approach spans, and substandard south approach alignment. In addition, the hydraulic analysis determined the structure is scour critical and scour mitigation will be required to maintain the structural integrity of the bridge. Bridge rehabilitation work will be conducted on the deck, piers, abutments, bent caps, hanger column, retaining wall, concrete railings, and approach spans. Deck drains will be removed, reconstructed, and refinished. The concrete railing will also be refinished, and the spalled and delaminated concrete will be patched. A hanger column will be removed and reconstructed, and the arch ribs from the spring line to the first column will be fiber wrapped. Piers 1, 2, and 3 will also be fiber wrapped. The pier curtain wall will be removed and reconstructed at Piers 1 and 2. Two cast-in-drilled-holes (CIDH) piling and pier footing overlays will be constructed at Piers 1, 2, and 3, and two CIDH piling and caps will be placed behind the abutments. Exterior girders and bent caps will be bolstered. The retaining wall on the south side of the bridge will be reconstructed, and 1 O feet of the approach span slab will be removed and reconstructed. Rock slope protection will be used to stabilize the creek bank around the abutments and prevent scour. Pier bents will have 5 to 7 feet of excavation immediately around them for installation of scour protection measures.
Road Approach Realignment - Stevenson Bridge Road will be realigned to eliminate two sharp turns just south and east of the bridge, one of which is a 90-degree curve. The roughly 1,000-foot realignment will go through an existing orchard and transition onto the existing road alignment near Strathgordon Lane. The realigned road will comply with County standards and provide for safer vehicle passage. Realignment of the south approach will require right of way (ROW) acquisition from one privately owned parcel, APN 0107-020-040. Fill will be needed to create the new roadway alignment. No buildings or other structures on the privately owned parcel will need to be relocated or removed as a result of the proposed realignment.
Staging Area - The area above the northeast creek bank between County Road 95A and the access road will be used as a staging area. General bridge construction equipment to be used includes, but is not limited to, haul trucks, backhoes, dump trucks, excavators, grade-alls, bulldozers, drilling, equipment, water trucks, concrete delivery trucks, and service vehicles.
Access Road and Temporary Creek Crossing - An access road will be cut in east of the bridge, on the north bank of Putah Creek, to access Piers 1 and 2. A temporary access road splits off from the permanent road at the top of the slope to access Pier 3. The access road will be composed of gravel and allow construction equipment to access the creek bed and the underside of the bridge. A creek crossing will be constructed between Piers 1 and 2, using either culverts and fill or a temporary low-span bridge.
Traffic Detour - Road closure will be required during road construction and bridge rehabilitation work. Traffic will be detoured using a loop along Stevenson Bridge Road, Sievers Road, Pedrick Road, Russell Boulevard, and Road 95A, with a maximum length of 13.7 miles.
Utility Relocation - Overhead poles with electric and phone lines occur along the south bridge approach, cross Putah Creek parallel to each side of the bridge, and continue north of the bridge. It is uncertain whether the poles and lines will need to be relocated. If relocation is necessary, the utility companies will be required to move the utilities prior to construction:
Contact Information
Name
Riley Martinson
Agency Name
Solano County
Job Title
Engineering Services Supervisor
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Unincorporated Winters
Counties
Solano
Regions
Unincorporated
Cross Streets
Strathgordon Lane, Rd 8036/Creeksedge Rd
Zip
95603
Total Acres
9.34
Parcel #
107-020-040, -050, -030-160, -030-170, 037-170-010, 038-160-014
Schools
Fairfield ES
Waterways
Putah Creek, Dry Slough
Other Location Info
Winters
Other Information
sec: unsectionalized portion of the Rio de Los Putos Land Grant
Notice of Determination
Approving Agency
Solano County Department of Resource Management
Approving Agency Role
Lead Agency
Approved On
County Clerk
Solano
Final Environmental Document Available at
675 Texas Street, Suite 5500, Fairfield, CA 94533
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Attachments
Notice of Determination
Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.