Phase 1 of the I-80/SR65 Interchange Project (Streambed Alteration Agreement No. 1600-2016-0291-R2)
4 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2016032019
- Lead Agency
- Caltrans 3 (Marysville) (California Department of Transportation, District 3)
- Document Title
- Phase 1 of the I-80/SR65 Interchange Project (Streambed Alteration Agreement No. 1600-2016-0291-R2)
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 8/3/2017
- Present Land Use
- Roseville:Community Commercial, Business Professional, Regional Commercial, Rocklin: Retail Commercial
- Document Description
- CDFW has executed Lake and Streambed Alteration Agreement No. 1600-2016-0291-R2, pursuant to Section 1602 of the Fish and Game Code to the project Applicant, Caltrans, as represented by Wayne Lewis. Project proposes to construct Phase 1 of the I-80/SR 65 interchange improvements (Caltrans EA 03-0H266U). The project is limited to improvements to the I-80/65 interchange and the Galleria Blvd/Stanford Ranch Road/SR 65 Northbound ramps in Placer County, CA to reduce future traffic congestion, improve operations and safety, and comply with current Caltrans and local agency design standards. Project will widen northbound SR 65 from the East Roseville Viaduct that crosses Antelope Creek to Pleasant Grove Blvd off-ramp, and widen and modify ramps at the Galleria Blvd/Stanford Ranch Rd/SR 65 interchange.
- Contact Information
-
Angela Calderaro
CDFW
1701 Nimbus Road, Suite A
Rancho Cordova, CA 95670
Phone : (916) 358-2920
Location
- Coordinates
- 38°46'41"N 121°15'57"W
- Cities
- Roseville
- Counties
- Placer
- Cross Streets
- Galleria Blvd./Stanford Ranch Road and SR 65
- Parcel #
- Various
- State Highways
- I-80, SR 65
- Schools
- Various
- Waterways
- Antelope Creek
Notice of Determination
- Approving Agency
- CDFW
- Approving Agency Role
- Responsible Agency
- Approved On
- Final Environmental Document Available at
- 1701 Nimbus Road, Suite A, Rancho Cordova, CA 95670
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.