Recycled Water Pipeline and Facility Upgrades

2 Documents in Project

Summary

SCH Number
2016031051
Lead Agency
San Elijo Joint Powers Authority
Document Title
Recycled Water Pipeline and Facility Upgrades
Document Type
NOD - Notice of Determination
Received
Posted
5/26/2016
Present Land Use
Public/Semi-Public, Right of Way, Recreation
Document Description
SEJPA proposes several recycled water pipelines extensions to serve existing land uses and relocations resulting from the development of the Caltrans North Coast Corridor Project as well as minor upgrades to SEWRF facilities. The recycled water pipeline extensions within Encinitas Ranch and Requeza Street would allow for conversion of several existing residential subdivisions and recreational trails to recycled water use. The recycled water relocations within Carol View Drive and Manchester Avenue would occur in response to the Caltrans North Coast Corridor (NCC) Project; both components are located within Caltrans ROW and within previously analyzed impact areas for the Caltrans NCC Project EIR/EIS. SEWRF facilities upgrades would include tertiary system upgrades and water reuse storage expansion.

Contact Information

Name
Mike Konicke
Agency Name
San Elijo Joint Powers Authority
Contact Types
Lead/Public Agency

Location

Cities
Encinitas
Counties
San Diego
Cross Streets
Manchester Avenue, Paseo De Las Flores, Requeza Street, Carol View Drive
Zip
many
Total Acres
4
Parcel #
2610101302
State Highways
I-5
Railways
NCTD
Schools
Cardiff Elem.
Waterways
San Elijo Lagoon, Pacific OCean

Notice of Determination

Approving Agency
San Elijo Joint Powers Authority
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print