State Route 128 Capell Creek Bridge Replacement Project (Lake or Streambed Alteration Agreement No. 1600-2017-0503-R3)

6 Documents in Project

Summary

SCH Number
2016022010
Lead Agency
California Department of Transportation, District 4
Document Title
State Route 128 Capell Creek Bridge Replacement Project (Lake or Streambed Alteration Agreement No. 1600-2017-0503-R3)
Document Type
NOD - Notice of Determination
Received
Posted
7/2/2018
Present Land Use
Transportation Facility
Document Description
CDFW has executed Lake and Streambed Alteration Agreement No. 1600-2017-0503-R3, pursuant to section 1602 of the Fish and Game Code to the project Applicant, Caltrans, District 4. Caltrans (Permittee) proposes to replace the existing Capell Creek Bridge with a new bridge and install a series horizontal drains along Capell Creek as well as a geo-tech wall. The existing reinforced concrete bridge and steel girder bridge will be replaced with a pre-cast/pre-stressed I-girder bridge with cast in place/reinforced concrete bents on the existing alignment. A temporary detour bridge will be installed adjacent and on the downstream side of the proposed bridge to carry traffic during demolition and bridge construction. The order of work will be as follows over 3 construction seasons; Season 1: clear and grub, install staging areas for temporary detour bridge and horizontal drain work, install temporary detour bridge and associated road widening, install temporary access road to construct creek diversion, install horizontal drains, demolish existing bridge and remove creek diversion. Installation of horizontal drains maybe delayed until Season 2. Season 2: site preparation, install creek diversion system, construct bridge abutments and piers, construct bride deck and roadway approaches, shift traffic to proposed bridge, remove temporary detour bridge and remove creek diversion. Season 3; Site Restoration.

Contact Information

Name
Robert Stanley
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Cities
Napa
Counties
Napa
Cross Streets
SR 128 from PM 19.7 to 20.7
Zip
94558
State Highways
128

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print