Permit No. 19532: Caltrans - I-80 Auxiliary Lanes Project

5 Documents in Project

Summary

SCH Number
2016012021
Lead Agency
California Department of Transportation, District 3 (DOT)
Document Title
Permit No. 19532: Caltrans - I-80 Auxiliary Lanes Project
Document Type
NOD - Notice of Determination
Received
Posted
11/20/2020
Document Description
Approval of Permit No. 19532, under California Code of Regulations, Title 23, Article 3, Section 6, for work within an adopted plan of flood control: To widen the existing Linda Creek Bridge (Bridge No. 19-0027) over Cirby Creek by adding a westbound lane to Interstate 80; to remove and replace an existing 24-inch diameter reinforced concrete pipe (RCP) with a new 24-inch diameter RCP pipe on the left (west) bank of the creek; to install a new 24-inch diameter RCP pipe on the right (east) bank of the creek; to construct a 15-foot concrete channel extension with cutoff wall across the main channel of Cirby Creek and under the widened portion of the bridge; to place concrete pavers on both banks of Cirby Creek; to install Rock Slope Protection (RSP) at the outfall of the drainage RCP pipes; and to install temporary falsework within the creek channel. The permit also authorizes the existing concrete lined channel and bridge that was originally constructed in 1955 and replaced in 1973.

Contact Information

Name
Itzia Rivera
Agency Name
Central Valley Flood Protection Board
Contact Types
Lead/Public Agency

Name
Agency Name
California Department of Transportation (Caltrans)
Contact Types
Project Applicant

Location

Cities
Roseville
Counties
Placer
Other Location Info
The project is located along Interstate 80 in southern Placer County and about 0.6 miles northeast of the Cirby Way undercrossing in Placer County.

Notice of Determination

Approving Agency
Central Valley Flood Protection Board
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Download CSV New Search Print