Apple Road over Fruit Channel Bridge Replacement

3 Documents in Project

Summary

SCH Number
2016012010
Lead Agency
Sacramento County
Document Title
Apple Road over Fruit Channel Bridge Replacement
Document Type
NOD - Notice of Determination
Received
Posted
2/24/2016
Present Land Use
Agricultural residential land uses are adjacent to the project alignment
Document Description
The proposed project is located on Apple Road approx. 3,300 feet southeast of Dillard Road and includes the replacement of an existing bridge structure over Fruit Channel along Apple Road. The project will result in the removal of an existing structure consisting of four corrugated metal pipes that are five feet in diameter and topped with concrete and asphalt. The existing structure is approx. 23 feet long and 27 feet wide. The existing approach roadway width is approx. 20 feet wide. The roadway and bridge currently accommodates two travel lanes. The existing structure was constructed in 1980 and is considered functionally obsolete. The Sacramento County DOT plans to replace this functionally obsolete bridge with a bridge that meets American Association of State Highway and Transportation Officials minimum standards. The new bridge will be the same approx. length as the existing bridge but will be widened to have an adequate curb to curb width, shoulders, bridge railings, and guardrails. The project work area, including the new bridge and approaches, will total approximately 270 lf and will extend approximately 120 ft west and 150 ft east of Fruit Channel respectively. The new bridge will accommodate two 11 ft travel lanes with 5 ft shoulders for automobile traffic and will be constructed as a concrete double culvert bridge. Each culvert will be constructed of reinforced concrete and will have a ht of six ft and a width of 10 ft and the bridge structure within Fruit Channel will be approximately 30 ft in length and 36 ft in width. The new bridge will raise the existing profile of Apple Rd by approximately 1.5 ft. Apple Rd will be closed adjacent to the proposed work area to allow for construction and staging. Approximately 370 ft of Apple Rd will be closed off and traffic utilizing Apple Rd will be rerouted to Berry, Orange and Dillard Rds. The length of the detour will be approximately 2.6 miles long and Apple Rd will be closed to through traffic for approximately six months.

Contact Information

Name
Cathy Hack
Agency Name
Sacramento County
Contact Types
Lead/Public Agency

Location

Counties
Sacramento
Cross Streets
Apple Road and Dillard Road
Zip
95693
Total Acres
0.58
Waterways
Fruit Channel; Cosumnes River
Township
7N
Range
7E
Base
MD
Other Location Info
Cosumnes

Notice of Determination

Approving Agency
Sacramento County
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print