Laguna Creek Trail - North Camden Spur Project (WLT005)

5 Documents in Project

Summary

SCH Number
2015122047
Lead Agency
City of Elk Grove
Document Title
Laguna Creek Trail - North Camden Spur Project (WLT005)
Document Type
NOD - Notice of Determination
Received
Posted
2/5/2016
Present Land Use
Land Use - Park, open space, agricultural residential, and low-density residential. General Plan - Multi-use Trail
Document Description
The City of Elk Grove proposes to extend a multi-use trail from the west end of the existing Laguna Creek Trail at the northern tip of Camden Park to MacDonald Park via Beckington Drive. The proposed project would connect the two longest segments of Laguna Creek Trail from the existing path at the northern tip of Camden Park for approximately 700 ft of Class 1 facility to south of White Peacock Court/Beckington Dr, and from White Peacock Court/Beckington Dr for approximately 200 ft of Class 1 facility to the existing path at MacDonald Park. Approximately 115 ft of existing Class 1 facility between homes facing White Peacock Court will require minor improvements and striping, and the approximate 1,050-ft Class 2 facility on Beckington Dr will require only striping. The proposed project will be constructed within existing public right of ways and street. The project is consistent with the EG General Plan, the EG Bicycle and Pedestrian Master Plan, and the EG Trails Master Plan. Each of these plans identifies the need for an off-street multiuse trail system providing connections throughout the City and the Sacramento region.

Contact Information

Name
Jessica Jordan
Agency Name
City of Elk Grove
Contact Types
Lead/Public Agency

Location

Cities
Elk Grove
Counties
Sacramento
Cross Streets
Beckington Drive and Camden Park and MacDonald Park
Zip
95624
Parcel #
Various

Notice of Determination

Approving Agency
City of Elk Grove
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print