Los Gatos HighSchool Classroom and Music Buildings

2 Documents in Project

Summary

SCH Number
2015122044
Lead Agency
Los Gatos-Saratoga Joint Union High School District
Document Title
Los Gatos HighSchool Classroom and Music Buildings
Document Type
NOD - Notice of Determination
Received
Posted
2/5/2016
Present Land Use
PLU: High School; Zoning: R-1 Single Family Residential; General Plan: Public/Quasi Public
Document Description
The LGSUHSD proposes to construct a classroom and music building on the portion of the Los Gatos High School (LGHS) campus that is currently developed in the maintenance yard, paved parking, and a portable classroom building. The proposed classroom building would be approximately 18,500 sf in size and two stories tall, with a max height of 35 ft. The classroom building would contain 10 classrooms, shared-use space, and ancillary uses such as restrooms. The proposed music building would be approximately 14,500 sf in size and one story tall with a max height of approximately 30 ft. The music building would contain numerous rooms for practice, rehearsal, and instrument storage, and ancillary uses such as restroom and equipment rooms. Prior to construction of the proposed classroom and music buildings, the existing maintenance yard would be demolished and the portable classroom building would be removed from the campus.

Contact Information

Name
Bob Mistele
Agency Name
Los Gatos-Saratoga Joint Union High School District
Contact Types
Lead/Public Agency

Location

Cities
Los Gatos
Counties
Santa Clara
Cross Streets
SR 17 and Los Gatos-Saratoga Road
Zip
95030
State Highways
17, 9
Schools
Los Gatos High School

Notice of Determination

Approving Agency
Los Gatos Saratoga Union HS District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print