Ramp Metering and Two Mixed Flow Lane at Shaw and Ashlan Avenues Southbound On-Ramp

3 Documents in Project

Summary

SCH Number
2015121057
Lead Agency
Caltrans 6 (Fresno) (California Department of Transportation, District 6)
Document Title
Ramp Metering and Two Mixed Flow Lane at Shaw and Ashlan Avenues Southbound On-Ramp
Document Type
NOD - Notice of Determination
Received
Posted
5/9/2016
Present Land Use
Residential and industrial

Document Description
Caltrans proposes to install ramp metering and two mixed flow lane and High Occupancy Vehicle (HOV) lane at the Shaw Avenue southbound on-ramp and Ashlan Avenue southbound on-ramp on SR 99, ramp metering system consists of: detectors, communication devices, electrical boxes and signals, construction of standard shoulders, and the installation of CHP enforcement pad. The project also includes construction of an Auxiliary lane on southbound SR 99 between the Olive Avenue on-ramp and Belmount Avenue off-ramp. To accomplish this project my need additional right of way for the proposed work.

Contact Information
G. William Trais Norris, III
California Department of Transportation, District 6
855 M Street, Suite 200
Fresno, CA 93710

Phone : (559) 445-6447

Location

Cities
Fresno
Counties
Fresno
Cross Streets
Ramp metering and two mixed flow lane at Shaw and Ashlan Avenues southbound on-ramp

Notice of Determination

Approving Agency
Caltrans
Approving Agency Role
Lead Agency
Approved On
Final Environmental Document Available at
855 M Street, Suite 200, Fresno, CA

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.