Document Description
The Inland Empire Utilities Agency (IEUA) and the Chino Basin Watermaster (CBWM) are proposing the Lower Day Basin Improvement Project (proposed project). The objective of this project ts to increase the recharge capacity (recycled water (RW) and stormwater (SW)) recharged into the Chino Groundwater Basin, specifically in the three cells located at Lower Day Basin. Under the Recharge Master Plan Update (RPMU), the proposed improvements for Lower Day Basin will increase recharge capacity by 789 acre feet per year by modifying the San Bernardino County Flood Control District's (SBCFCD) diversion channel, installing a control gate valve on Cell 3's midlevel outlet, and improving the Basin embankments. The proposed project includes modifications to the Basin inlets and outlets that will allow more storm water to be diverted into the Basin and stored at higher elevations for longer durations. There will be no modifications to the physical size, layout/configuration or storage volume of the Basin. The proposed improvements will allow the Basin operations to be modified to achieve increased groundwater recharge.

Contact Information

Name
Joel Ignacio
Agency Name
Inland Empire Utilities Agency
Contact Types
Lead/Public Agency

Location

Cities
Rancho Cucamonga
Counties
San Bernardino
State Highways
Interstate 210
Waterways
Day Creek channel
Township
1N
Range
6W
Section
31
Base
SBM
Other Location Info
The proposed project site consists of an existing basin with several cells. The Lower Day Basin is located immediately south of Interstate 210; immediately west of Day Creek channel; about 1/4 mile north of Base Line Road; and immediately east of Rochester Avenue. The project location is depicted on the USGS Cucamonga Peak 7.5 Topographic Quadrangle map. Specifically, the project is located within Section 31, Township 1 North, Range 6 West, San Bernardino Base and Meridian.

Notice of Determination

Approving Agency
Inland Empire Utilities Agency
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A