CDFW LSA State-mandated Wastewater Treatment and Outfall Improvement Project

5 Documents in Project

Summary

SCH Number
2015112045
Lead Agency
City of Mount Shasta
Document Title
CDFW LSA State-mandated Wastewater Treatment and Outfall Improvement Project
Document Type
NOD - Notice of Determination
Received
Posted
9/15/2021
Document Description
The project is limited to improvements to existing outfall infrastructure and replacement of the diffuser pipe in the Sacramento River. A replacement 17-foot-long river diffuser will be installed at the same location on the riverbank as the existing 5-foot-long diffuser, but rotated down to be completely submerged during low-flow periods. Some submerged rock will be shifted to allow the new diffuser to be installed. The work area will be limited to 10 feet on either side of the dissipation tank, outfall pipeline, and diffuser, and out towards the centerline of the river. Up to 1 lineal foot of the Sacramento River will be permanently impacted and up to approximately 0.01 acres (± 21 lineal feet) of the Sacramento would be temporarily impacted by work occurring within the ordinary high-water mark. Because of the steepness of Box Canyon, the Permittee proposes that the use of a helicopter may be required to transport heavy equipment (i.e. air hammer and pipe) to the work area for improvements to the diffuser.

Contact Information

Name
Helen Bowman
Agency Name
California Department of Fish and Wildlife
Contact Types
Responsible Agency

Location

Cities
City of Mount Shasta
Parcel #
036-450-240
Waterways
Sacramento River

Notice of Determination

Approving Agency
California Department of Fish and Wildlife
Approving Agency Role
Responsible Agency
Approved On
County Clerk
Shasta
Final Environmental Document Available at
City of Mount Shasta

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print