Alessandro Pond Optimization Project (Project); Clean Water State Revolving Fund (CWSRF) No. C-06-8165-110

4 Documents in Project

Summary

SCH Number
2015111005
Lead Agency
Eastern Municipal Water District (EMWD)
Document Title
Alessandro Pond Optimization Project (Project); Clean Water State Revolving Fund (CWSRF) No. C-06-8165-110
Document Type
NOD - Notice of Determination
Received
Posted
2/20/2018
Present Land Use
Public Facility/A-2-10 and OSG/AG & WS
Document Description
Project would maximize operational storage and enhance operation of the pump station at the Districts Allessandro Recycled Water Storage Pond Facility. Recent configuration of the ponds and completion of the pump station necessitates the need to enhance the integrated operation of the facility and to optimize pond storage. The project would protect the slopes from erosion, optimize storage, and enhance operation of the pump station by implementing erosion protection measures, re-grading the ponds, adjusting pipelines and appurtenances to grade, and implementing electrical improvements that include Supervisory Control and Data Acquisition-controlled motor operated valves which will add safety features that would ensure that the potential high water levels would not exceed the berm height.

Contact Information

Name
Cedric Irving
Agency Name
SWRCB
Contact Types
Lead/Public Agency

Location

Cities
San Jacinto
Counties
Riverside
Cross Streets
Alessandro and Ramona Expressway
Zip
92583
Total Acres
2.85
Parcel #
443-070-018,019,020,021,031
State Highways
79
Waterways
San Jacinto River
Township
4S
Range
1W
Section
23,25,
Base
SBB&M

Notice of Determination

Approving Agency
State Water Board
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print