Water Treatment Plant Replacement - 2015

3 Documents in Project

Summary

SCH Number
2015102087
Lead Agency
Donner Summit Public Utility District
Document Title
Water Treatment Plant Replacement - 2015
Document Type
NOD - Notice of Determination
Received
Posted
12/18/2015
Present Land Use
FOR - 40, Forest - 40 acre minimum parcel size
Document Description
The project will involve improvements to the existing water system in order to correct deficiencies in the existing treatment process. The proposed project involves the construction, operation, and maintenance of new filters, expansion of the existing treatment plant building, improvements to the existing clearwell, elimination of existing cross connections, improvements to chemical feed systems, improved backwash reclamation facilities, improvements to electrical controls, telemetry, and instrumentation, and replacement of the existing generator. The project as proposed will directly benefit the entire system. The project will assure provision of a safe reliable source of drinking water in compliance with State Division of Drinking Water standards.

Contact Information

Name
Tom Skjelstad
Agency Name
Donner Summit Public Utility District
Contact Types
Lead/Public Agency

Location

Counties
Nevada
Cross Streets
Donner Pass Road and Donner Ski Ranch Road
Zip
95728
Total Acres
.10
Parcel #
17-030-08-000
State Highways
I-80
Railways
UPRR
Airports
No
Schools
No
Waterways
Lake Angela, South Yuba River, Lake Mary
Township
17N
Range
15E
Section
16
Base
MDB&M
Other Location Info
Norden

Notice of Determination

Approving Agency
Donner Summit Public Utility District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes