Cabrillo Power I LLC Encina Marine Oil Terminal Decommissioning Project
3 Documents in Project
Summary
SCH Number
2015101064
Lead Agency
California State Lands Commission
Document Title
Cabrillo Power I LLC Encina Marine Oil Terminal Decommissioning Project
Document Type
NOD - Notice of Determination
Received
Posted
12/18/2015
Present Land Use
PU - Public Utility
Document Description
Cabrillo Power I LLC proposes to decommission the Encina Marine Oil Terminal (MOT), which is a component of the Encina Power Station. The Project is comprised of the following elements: 1) removal of the entire fuel oil submarine pipeline; 2) decommissioning of related onshore facilities; 3) temporary removal of the riprap groin to remove the fuel oil submarine pipeline; 4) restoration of the riprap groin and beach; 5) removal of several components of the offshore MOT, including anchors, chains, and buoys/moorings; 6) removal of all seafloor debris associated with the MOT; and 7) quit claim of the remaining portions of the underpass to the City of Carlsbad. Decommissioning is schedule to commence in September 2016 and finish January 2018. The State Lands Commission activities is an approval of a 5-yr General Lease - Industrial Use, beginning March 24, 2015, through March 23, 2020, and authorization to accept a quitclaim deed for the termination of the lease.
Contact Information
Name
Alan Scott
Agency Name
California State Lands Commission
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Carlsbad
Counties
San Diego
Cross Streets
Carlsbad Boulevard
Zip
92008
Total Acres
95
State Highways
I-5
Railways
Freight/Cummuter
Airports
No
Schools
Jefferson ES
Waterways
Pacific Ocean, Aqua Hedionda Lagoon
Township
12S
Range
5W
Section
1
Base
SBB&M
Notice of Determination
Approving Agency
California State Lands Commission
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.