San Sevaine Basin Improvements (Project); Clean Water State Revolving Fund (CWSRF) No. C-06-8105-120
3 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2015101054
- Lead Agency
- Inland Empire Utilities Agency (Inland Empire Utility Agency)
- Document Title
- San Sevaine Basin Improvements (Project); Clean Water State Revolving Fund (CWSRF) No. C-06-8105-120
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 10/25/2017
- Document Description
- Project includes the extension of the recycled water pipeline to Basins 1-3. The new pipeline would extend from the existing recycled water pipeline to Basins 1-3. The new pipeline would extend from the existing recycled water pipeline adjacent to the Etiwanda Channel along existing maintenance roads to the north side of Basin 1, which is located just south of Wilson Avenue. Three turnouts (inlets/outlet structures) would be provided, one into each Basins 1, 2, and 3. The new pipeline would be a 30-inch (30") diameter pipeline from the existing turnout of the Basins. Pipe length is estimated to be approx. 4,600 linear feet and an additional 300 lineal feet of 24" pipeline would also need to be installed.
- Contact Information
-
Carina Grove
SWRCB
1001 I St., 16th Floor
Sacramento, CA 95814
Phone : (916) 327-9401
Location
- Coordinates
- 34°8'6.5"N 117°29'47"W
- Cities
- Rancho Cucamonga
- Counties
- San Bernardino
- Cross Streets
- Wilson Avenue / I-15 & I-210
- Total Acres
- 130
- State Highways
- I-15 and 210
- Township
- 1N
- Range
- 6W
- Section
- 26/27
- Base
- SBB&M
Notice of Determination
- Approving Agency
- State Water Board
- Approving Agency Role
- Responsible Agency
- Approved On
- Final Environmental Document Available at
- 1001 I Street, 16th Floor, Sacramento, CA 95814
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.