Charleston Retention Basin Improvement Project

3 Documents in Project

Summary

SCH Number
2015092068
Lead Agency
City of Mountain View
Document Title
Charleston Retention Basin Improvement Project
Document Type
NOD - Notice of Determination
Received
Posted
12/4/2015
Present Land Use
GP: Parks, Schools, & City Facilities, High-Intensity Office; Z: Flood Plain and P(39) North Bayshore Precise Plan
Document Description
The project includes a Planned Community Permit for a habitat expansion and restoration project around the Charleston Retention Basin including the removal of 134 existing parking spaces to allow for new planting areas, the comprehensive replanting of the upland basin areas with native plants and trees, the realignment and improvement of the existing pedestrian path around the basin, a new separate bicycle path in the southwestern quadrant, and two new pedestrian bridges across the basin; and a Heritage Tree Removal Permit to allow the removal of 119 Heritage trees.

Contact Information

Name
Stephanie Williams
Agency Name
City of Mountain View
Contact Types
Lead/Public Agency

Location

Cities
Mountain View
Counties
Santa Clara
Cross Streets
North Shoreline Boulevard and Charleston Road
Zip
94043
Total Acres
14
Parcel #
116-11-012 to -014, -020, -027, -036
State Highways
US 101, SR 85
Railways
Caltrain, UPRR
Airports
Moffett Fedi Airfield, Palo Alto
Schools
Mtn View-Whisman Dist
Waterways
Stevens Creek, SF Bay
Township
6S
Range
2W
Base
MDB&M

Notice of Determination

Approving Agency
Mountain View City
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print