New Model Colony East Bridges Over Cucamonga Creek and Deer Creek Flood Control Channels at Schaeler Avenue
2 Documents in Project
Summary
SCH Number
2015091065
Lead Agency
City of Ontario
Document Title
New Model Colony East Bridges Over Cucamonga Creek and Deer Creek Flood Control Channels at Schaeler Avenue
Document Type
NOD - Notice of Determination
Received
Posted
11/9/2015
Present Land Use
County right-of-way flood control Channel (Cucamonga Creek and Deer Creek).
Document Description
The proposed Project implements projects previously approved by the City of Ontario, consisting of construction of two replacement and two new bridges (Project) over the concrete-lined Cucamonga/Deer Creek flood control channels at Schaefer Avenue, Edison Avenue, Eucalyptus Avenue and Merrill Avenue. The San Bernardino County Flood Control District right-of-way defines the Project limits. Project operational impacts, growth inducing impacts and cumulative impacts were previously analyzed in The Ontario Plan (TOP) EIR and in the Addendum to TOP EIR for the City's Master Plan of Streets and Highways (MPSH). The bridges would be constructed consecutively and during two phases, timed to meet traffic demand resulting from implementation of TOP and the MPSH.
Contact Information
Name
Scott Murphy
Agency Name
City of Ontario
Contact Types
Lead/Public Agency
Phone
Location
Cities
Ontario
Counties
San Bernardino
Cross Streets
Archidbald Avenue and Schaefer/Edison/Eucalyptus/Merrill Avenues
Zip
91764
State Highways
SR 60
Railways
No
Airports
Chino
Schools
Archibald Christian Preschool
Waterways
Cucamonga Creek and Deer Creek Flood Control
Notice of Determination
Approving Agency
City of Ontario
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No