PG&E Former San Luis Obispo - 1 Manufactured Gas Plant Remedial Action Plan

2 Documents in Project

Summary

SCH Number
2015091013
Lead Agency
Department of Toxic Substances Control
Document Title
PG&E Former San Luis Obispo - 1 Manufactured Gas Plant Remedial Action Plan
Document Type
NOD - Notice of Determination
Received
Posted
11/16/2015
Present Land Use
commercial
Document Description
DTSC has approved a RAP for the PG&E Former San Luis Obispo-1 Manufactured Gas Plant Site pursuant to regulatory authority granted under Chapter 6.8, Division 20, sections 25323.1 and 25356.1, H&SC. The Draft RAP, dated March 25, 2015, was prepared by Terra Pacific Group for PG&E and is incorporated as reference herin. The purpose of the project is to address impacts to soil and groundwater from previous operations on Site. Remedial activities will involve excavation and disposal of approximately 20,000 tons of contaminated soil at an off-site permitted facility. The soil is impacted by polycyclic aromatic hydrocarbons, arsenic, lead, and petroleum hydrocarbons. Additionally, approximately the same amount of clean backfill will be imported from a quarry located in Santa Margartia, CA, approximately 14 mi north of the site. The imported fill will be tested for contaminants in accordance with DTSCs October 2001 Imported Advisory on Clean Fill Material.

Contact Information

Name
Jeff Gymer
Agency Name
Department of Toxic Substances Control
Contact Types
Lead/Public Agency

Location

Counties
Kern
Cross Streets
Pismo / Walker
Zip
93401
Total Acres
.85
Parcel #
002-505-005, 006
State Highways
Hwy 1
Railways
SPRR
Airports
No
Schools
Hawthorne ES 0.5 mi SE of site
Waterways
San Luis Obispo Creek 0.10 mi west of site
Township
30S
Range
12E
Base
MDB&M

Notice of Determination

Approving Agency
DTSC
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print