Corralitos Creek Diversion Operations and Maintenance Project

3 Documents in Project

Summary

SCH Number
2015082054
Lead Agency
City of Watsonville
Document Title
Corralitos Creek Diversion Operations and Maintenance Project
Document Type
NOD - Notice of Determination
Received
Posted
8/29/2016
Document Description
Project is limited to the operations and maintenance of a surface water diversion and fishway facilities in Corralitos Creek. The diversion structure consists of a weir across the stream channel and an upstream intake tower. The weir is concrete and is approx. 8.5 feet tall, 35 feet wide and 52.5 feet in length. The weir includes a 31-foot ogee type spillway in the channel along the left bank (look downstream) and a fish ladder along the right bank. Flows are diverted through the intake tower on the left bank about 25 feet upstream of the weir and the maximum instantaneous rate of surface water withdrawal is 3.9 cubic feet per second. The Permittee claims basis of right to divert water under a pre-1914 diversion right. The CDFW is executing a Lake and Streambed Alteration Agreement No. 1600-2015-0201-R3 pursuant to Section 1602 of the Fish and Game Code to the project Applicant, City of Watsonville as represented by Steve Palmisano.

Contact Information

Name
Melissa Farinha
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Cities
Watsonville
Counties
Santa Cruz
Cross Streets
Eureka Canyon Rd approx 1.3 mi north of Browns Valley Rd (460 EC Rd)
Zip
95076
Total Acres
1
Parcel #
107-121-66
Schools
Bradley ES
Waterways
Corralitos Creek
Township
11S
Range
1E
Section
12
Base
4

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A