West Tahoe Regional Water Treatment Plant Project

5 Documents in Project

Summary

SCH Number
2015082021
Lead Agency
Tahoe City Public Utility District
Document Title
West Tahoe Regional Water Treatment Plant Project
Document Type
NOD - Notice of Determination
Received
Posted
3/17/2021
Document Description
The State Water Resources Control Board (State Water Board) is a Responsible Agency for the Project. The State Water Board’s Drinking Water State Revolving Fund (SRF) Program is financing the Project. The Tahoe City Public Utilities District is proposing to construct a new West Lake Tahoe Regional Water Treatment Plant (WLTRWTP) to address water supply issues for the McKinney-Quail Water Service Area, and to provide a regional drinking water supply solution for the west shore area of Lake Tahoe. The WLTRWTP components include installation of two intake pumps with a power line that runs between intake pumps and the electrical/chemical feed room, replacement of the existing intake pipeline with a pipeline from the intake facilities to the WLTRWTP, construction of an intake pump station and chemical feed room, and construction of a water treatment facility. Construction activities also include decommission and removal of the existing interim surface water treatment plant, lake intake pump station, and concrete vault.

Contact Information

Name
Gabriel Edwards
Agency Name
State Water Resources Control Board
Contact Types
Responsible Agency

Location

Counties
Placer
Cross Streets
Lodge Drive between Flicker Avenue and SR 89
Zip
96142
Total Acres
6.5
Parcel #
098-330-004
State Highways
Hwy 89
Waterways
McKinney Creek, Lake Tahoe, Quail Crk, General Crk
Township
14N
Range
17E
Section
7
Other Location Info
Tahoma

Notice of Determination

Approving Agency
State Water Resources Control Board
Approving Agency Role
Responsible Agency
Approved On
County Clerk
Placer
Final Environmental Document Available at
http://www.tahoecitypud.com/

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print