Padre Dam Municipal Recycling Facility, Phase 1 Expansion (Project); Clean Water State Revolving Fund (CWSRF) No. C-06-8133-110

3 Documents in Project

Summary

SCH Number
2015071078
Lead Agency
Padre Dam Municipal Water District
Document Title
Padre Dam Municipal Recycling Facility, Phase 1 Expansion (Project); Clean Water State Revolving Fund (CWSRF) No. C-06-8133-110
Document Type
NOD - Notice of Determination
Received
Posted
3/9/2017
Present Land Use
LUD: "Public" in City of Santee General Plan Z: Park/Open Space in City of Santee Zoning Ordinance.
Document Description
The project would expand the existing WRF capacity from 2 million gallons per day to 6 MGD. This would be accomplished by installing additional conventional treatment facilities. This would be accomplished by installing additional conventional treatment facilities, converting biological basins to nitrogen removal only, installing a 2.2 MGD advanced water treatment plant, and upgrading pumps at the off-site influent pump station. New equipment to be constructed includes the influent pump station, a 6 MGD headworks facility, an additional 3.1 MGD of primary clarifier capacity, an additional 4 MGD of secondary clarifier capacity, a 0.9 million gallon flow equalization basin, 2 filters, and solar panels to provide 17% of the energy required for project operation. The current biological aeration basins would be converted to nitrification and denitrification process.

Contact Information

Name
Amanda Dwyer
Agency Name
SWRCB
Contact Types
Lead/Public Agency

Location

Cities
Santee
Counties
San Diego
Cross Streets
West of Sycamore Canyon Road, north of Carlton Oaks Drive
Zip
92071
Total Acres
7.5
Parcel #
37601005 / 37602004
State Highways
SR 52
Schools
Sycamore Canyon
Waterways
San Diego River
Township
15S
Range
1W

Notice of Determination

Approving Agency
State Water Board
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print