MND for the Ray Stoyer Water Recycling Facility (WRF)

3 Documents in Project

Summary

SCH Number
2015071078
Lead Agency
Padre Dam Municipal Water District
Document Title
MND for the Ray Stoyer Water Recycling Facility (WRF)
Document Type
NOD - Notice of Determination
Received
Posted
10/9/2015
Present Land Use
LUD: "Public" in City of Santee General Plan Z: Park/Open Space in City of Santee Zoning Ordinance.
Document Description
The project consists of expanding the capacity of the Ray Stoyer WRF from 2 million gallongs per day (mgd) to 6 mgd. The capacity would be increased by installing additional conventional treatment facilities, converting biological basins to nitrogen removal only, installing a 2.2 mgd (annual average) advanced water treatment plant (AWTP), and upgrading pumps at an off-site influent pump station. The project would allow additional recycled water to be provided to the customers within the Padre Dam Western Service Area, which would reduce potable water use consumption. The project also would enable Padre Dam to proudce highly treated recycled water, or purified water (using free chlorination, micro-filtration, reverse osmosis, and advanced oxidation) for potable reuse purposes. Purified water produced from the project would be sent to a Santee Groundwater Basin for injection into the aquifer or to Lake Jennings for surface water augmentation (which is not a part of the proposed project).

Contact Information

Name
Arne Sandvik
Agency Name
Padre Dam Municipal Water District
Contact Types
Lead/Public Agency

Location

Cities
Santee
Counties
San Diego
Cross Streets
West of Sycamore Canyon Road, north of Carlton Oaks Drive
Zip
92071
Total Acres
7.5
Parcel #
37601005 / 37602004
State Highways
SR 52
Schools
Sycamore Canyon
Waterways
San Diego River
Township
15S
Range
1W

Notice of Determination

Approving Agency
PDMWD
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print