PA-1400203 (SA) Site Approval Application
2 Documents in Project
Summary
SCH Number
2015062095
Lead Agency
San Joaquin County
Document Title
PA-1400203 (SA) Site Approval Application
Document Type
NOD - Notice of Determination
Received
Posted
10/16/2015
Present Land Use
The Property is zoned I-G (General Industrial) and the General Plan Designation is I/G (General Industrial).
Document Description
A site approval application no. PA-1400203 of Oldcastle Precast, Inc. to expand the existing concrete manufacturing facility in three phases over five years. Phase 1 is the construction of a 6,000 sf office, a new parking area, and a new entrance on Mariposa Road. Phase 2, with building permits to be issued within three years, includes the construction of a 24,000 sf production building and an 8,750-sf steel fabrication building. Phase 3, with building permits to be issued within five years, includes the construction of a 12,000 sf production building and a 2,500 sf maintenance building. This project is not under Williamson Act contract. The property is zoned I-G and the General Plan designation is I/G.
Contact Information
Name
Sonia Serrano
Agency Name
San Joaquin County Comm. Dev. Department
Contact Types
Lead/Public Agency
Phone
Location
Cities
Stockton
Counties
San Joaquin
Cross Streets
Mariposa Road, St. Rt. 99 E. Frontage Road
Zip
95215
Total Acres
27.86
Parcel #
179-550-07 & 18
State Highways
St. Rt. 99, St. Rt. 4
Waterways
Duck Creek, Little Johns Creek, Mormon Slough
Notice of Determination
Approving Agency
San Joaquin County
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.