Penitencia Deliver Main and Penitencia Force Main Seismic Retrofit Project

3 Documents in Project

Summary

SCH Number
2015062061
Lead Agency
Santa Clara Valley Water District
Document Title
Penitencia Deliver Main and Penitencia Force Main Seismic Retrofit Project
Document Type
NOD - Notice of Determination
Received
Posted
9/28/2015
Present Land Use
Lower Hillside; Public/Quasi-Public; Open Space, Parkland and Habitat; Residential Neighborhood
Document Description
The objective of the proposed project is to perform a seismic retrofit of the Penitencia Delivery Main, Penitencia Force Main, South Bay Aqueduct, and Finished Meter Vault to accommodate the creek and potentially extensive seismically-induced movements of the active Penitencia Creek Landslide over a 50-year design life. The proposed project would include: temporary shutdown of the Penitencia Water Treatment Plant, dewatering of the existing pipelines, installation of replacement compression pipelines, site restoration, and construction of ancillary facilities.

Contact Information

Name
Tiffany Hernandez
Agency Name
Santa Clara Valley Water District
Contact Types
Lead/Public Agency

Location

Cities
San Jose
Counties
Santa Clara
Cross Streets
Piedmont Avenue, Grossmont Drive, Whitman Way
Zip
95132
Total Acres
7
State Highways
Hwy 680
Schools
Noble ES
Waterways
Sierra Creek, Berryessa Creek, Coyote Creek

Notice of Determination

Approving Agency
Santa Clara Valley Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.