Foothill Trunk Replacement Project (Streambed Alteration Agreement No. 1600-2016-0047-R2)

3 Documents in Project

Summary

SCH Number
2015062042
Lead Agency
South Placer Municipal Utility District (SPMUD)
Document Title
Foothill Trunk Replacement Project (Streambed Alteration Agreement No. 1600-2016-0047-R2)
Document Type
NOD - Notice of Determination
Received
Posted
7/28/2016
Present Land Use
Single and multi-family residential
Document Description
CDFW has executed Lake and Streambed Alteration Agreement No. 1600-2016-0047-R2, pursuant to section 1602 of the Fish and Game Code to the project Applicant, South Placer Municipal Utility District. Project includes the installation of a sewer pipeline along Aguilar Creek to replace an existing, deteriorating pipeline between El Don Drive and Secret Ravine. One segment of the pipeline would cross an oxbow channel along the creek west of Aguilar Road, and another segment would cross a man-made pond along the creek between Arrowhead Drive and El Don Dr., requiring installation of a temporary dam (sand/clay bags) along the pond (although water is not likely to be present during construction). The pipeline would cross Aguilar Creek beneath an existing culvert in Aguilar Road; the culvert would not be affected by pipeline installation (trenchless construction methods would be used.

Contact Information

Name
Angela Calderaro
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Cities
Rocklin
Counties
Placer
Cross Streets
El Don Drive, Aguilar Road
Total Acres
4
State Highways
I-80
Waterways
Aguilar Creek
Township
11N
Range
7E
Section
20
Base
MDB&M

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print