Foothill Trunk Replacement Project
3 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2015062042
- Lead Agency
- South Placer Municipal Utility District (SPMUD)
- Document Title
- Foothill Trunk Replacement Project
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 10/6/2015
- Present Land Use
- Single and multi-family residential
- Document Description
- SPMUD is proposing to replace its Foothill Trunk line, a 12-inch-diameter gravity sewer pipeline, with a new 24-inch-diameter pipeline in Rocklin, Placer County. The new pipeline would be approximately 2,300 feet long and would be installed either in the same alignment as or parallel to the existing pipeline or along a new alignment at depths of 5-17 feet below the ground surface. A temporary dam would be placed in Aguilar Creek to allow pipeline installation beneath a ponded area of the creek. Pipeline would be installed using primarily open-cut construction. Standard BMPs, dust control, and other measures would be implemented during construction.
- Contact Information
-
Herb Niederberger
South Placer Municipal Utility District
Lead/Public Agency
5807 Springview Drive
Rocklin, CA 95677
Phone : (916) 786-8555
Location
- Cities
- Rocklin
- Counties
- Placer
- Cross Streets
- El Don Drive, Aguilar Road
- Total Acres
- 4
- State Highways
- I-80
- Waterways
- Aguilar Creek
- Township
- 11N
- Range
- 7E
- Section
- 20
- Base
- MDB&M
Notice of Determination
- Approving Agency
- South Municipal Utility District
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- http://spmud.ca.gov/ 5807 Springview Drive, Rocklin, CA 95677
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.