SMUD Rancho Seco Solar PV Project (California Endangered Species Act Incidental Take Permit No. 2081-2016-006-02 (ITP))

3 Documents in Project

Summary

SCH Number
2015062040
Lead Agency
Sacramento Municipal Utility District
Document Title
SMUD Rancho Seco Solar PV Project (California Endangered Species Act Incidental Take Permit No. 2081-2016-006-02 (ITP))
Document Type
NOD - Notice of Determination
Received
Posted
6/23/2016
Present Land Use
Permanent Agriculture, 80-acre minimum (AG-80)
Document Description
CDFW has executed CA Endangered Species Act Incidental Take Permit No. 2081-2016-006-02, pursuant to section 2081 (b) of the Fish and Game Code to the project applicant, Rancho Seco Solar, LLC. The project involves the construction of a 10-MW alternating current (ac) Photovoltaic (PV) solar power facility. Proposed infrastructure improvements included energy-related facilities and road improvements. Construction-related activities are below. The total project area encompasses 75-acres, witht he solar facility, occupying approx. 65-acres. Project features include PV solar power plant infrastructure, a 45-foot long overhead sub-transmission line and interconnection equipment, a substation, and switchgear. Approx. 10-acres will be temporarily used for construction staging and temporary construction office trailers. The Project will not result in impacts to CA tiger salamander habitat; the Project will not permanently remove and CA tiger salamander habitat. The project is expected to result in incidental take of CA tiger salamander, which is designated as a threatened species under CESA.

Contact Information

Name
Tanya Sheya
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Counties
Sacramento
Cross Streets
Approx. 3.5 miles east of Clay Station Road and Twin Cities Road (Hwy 104)
Zip
95852
Total Acres
75
Parcel #
140-0050-008-0000
State Highways
Hwy 104
Railways
UPRR
Waterways
Clay Creek
Township
6N
Range
8E
Section
29
Other Location Info
Herald

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.