First Line of Defense (FLOD) Facilities Maintenance Project
3 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2015061111
- Lead Agency
- San Bernardino Flood Control District
- Document Title
- First Line of Defense (FLOD) Facilities Maintenance Project
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 10/15/2015
- Document Description
- To conduct maintenance within 33 district flood control facilities (including dams, basins, and spreading grounds). These facilities provide protection to the residents of the areas surrounding the facilities during storm events, by containing flows and collecting large amounts of debris that flush down out of the mountains. Permitted maintenance of the project facilities would provide flood protection for the next five years to adjacent and downstream public and private property, as well as other district facilities connected to the flood control system.
- Contact Information
-
Erma Hurse
San Bernardino Flood Control District
Lead/Public Agency
825 E. Third Street, Room 123
San Bernardino, CA 92415-0835
Phone : (909) 387-8109
Location
- Cities
- San Bernardino
- Counties
- San Bernardino
- Cross Streets
- Multiple
- Zip
- Multiple
- Total Acres
- 892.35
- State Highways
- Hwy 210
- Railways
- No
- Airports
- Redlands Municipal
- Waterways
- Santa Ana River
Notice of Determination
- Approving Agency
- San Bernardino County
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- 825 Third Street, Rm 123, San Bernardino, CA 92415-0835
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.