Roundhouse Area Improvements Project

2 Documents in Project

Summary

SCH Number
2015052062
Lead Agency
Port of Oakland
Document Title
Roundhouse Area Improvements Project
Document Type
NOD - Notice of Determination
Received
Posted
4/19/2016
Present Land Use
Heavy Industrial (M40)
Document Description
The Port of Oakland (Port) Roundhouse Area Improvements Project reconfigures the Port's existing approx. 37-acre former Union Pacific (UP) Roundhouse area and adjacent 5-acre former Sherex Chemical property, along with adjacent access driveways and rail (collectively referred to herein as "the Roundhouse Area" or "the Project site") to improve the utilization of the site to better support the Port's maritime business. The site has most recently been used for public and private drayage truck and equipment parking. The Project consists of construction, leasing, operation and maintenance of a rail-served grain transloading operation (grain terminal) on approx. 15 acres at the project site, including construction of two temporary grain handling buildings, installation of utilities, new and upgraded railroad track with switches and related equipment, access driveway, and grain unloading and loading equipment, including an uploading pit and grain elevator. Ancillary structures, gates, fences, and similar support structures will also be built. Other potential uses evaluated for the project site include other bulk cargo transloading facilities, warehousing, truck parking, cargo and equipment storage and expansion of the adjacent marine terminal. Such projects would include related construction, leasing, operations and maintenance, and impacts would not exceed those of the proposed grain terminal. Dedicated parking for Union Pacific Railroad (5.9 acres) will remain on the site as a suitable location. The former UP Roundhouse area is subject to a Covenant and Environmental Restriction on Property (deed restriction) and an associated Revised Site Management Plan (SMP); compliance with the SMP is required for all development, operations, and maintenance. In addition, standard Port construction best management practices are integral to activities at the Project site. The current proposed project is to lease the Project site to expand the adjacent marine terminal activities into the property. Expansion of the terminal may require minor construction, such as minor utility improvements, moving fences, restriping pavement and providing modular buildings for on-site offices and security.

Contact Information

Name
Tim Leong
Agency Name
Port of Oakland
Contact Types
Lead/Public Agency

Location

Cities
Oakland
Counties
Alameda
Cross Streets
1401 Middle Harbor Road
Zip
94607
Total Acres
42
Parcel #
18-395-8-3, 18-395-9, 18-395-4
State Highways
I-880 and 580
Railways
Amtrak, UP, BNSF
Schools
Columbia College
Waterways
Oakland Inner Harbor, San Francisco Bay

Notice of Determination

Approving Agency
Port of Oakland
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.